Kazakhstan——3-4Ton/Hour Alfalfa Pellet Line 

Project Brife Introduction:

1.Project Name:Alfalfa Pellet Line

2.Raw Materisl: Bales of  Alfalfa

3.Moisture Of Raw Material: Wet Type 40-55% 

4.Capacity:3-4 Ton/Hour

5.Proecss: Grinding Process-Fine Crushing Process-Drying Process-Pellet Process-Cooling Process-Packing Process

6.Main Machine:Straw Cutter,Hammer Mill, Rotary Drum Dryer,TONY Pellet MachineTYJ551-Ⅲ-132kw,Pellets Coller,Ton Packing Machine,  And Belt Conveyors

7.Total Power: About 456KW

8.Need Area: About 500-600㎡

9.Project Country: Kazakhstan

10.Voltage:220V,50HZ

Production process:

Equipment list:

It mainly contains the following steps and machines as following:

1.To Use TONY Straw Cutter To Grind Alfalfa Balesφ ≤2200mm Into 60-70mm Pieces.

2.To Use TONY Hammer Mill To Crush 60-70mm Bigger Pieces Into 8-14mm Sawdust.

3.To Use TONY Rotary Drum Dryer To Dry The 40-55% Sawdust Into 10-15% Sawdust

5.To Use TONY Vertical Ring Die Pellet Machine To Products Pellets With φ6-8mm.

6.To Use TONY Galvanized Coller To Cool Pellets From 80-90℃ To 20-30℃.

You Can Contact TONY To Get For More Details Information And Quoation.

Customer Site:

Installation and commissioning arrangement after receiving the equipment:

If all the equipment you ordered from TONY has been received, please inform us in time. And prepare the following information in advance so that we can arrange technicians to guide the installation and commissioning.

Material preparation:

1. Your factory photos, raw material photos, transformer photos, big line to the workshop photos.

2. If you need to prepare your own auxiliary equipment (such as: conveying, pit, foundation, hot blast stove, etc.), these should also provide photos. And you need to send a video of the normal operation of the auxiliary equipment you prepared in advance. (You need to install and run the non-TONY equipment in advance)

3. You need to prepare for industrial closed gear oil (the gear box is not injected with gear oil when the granulator leaves the factory, you need to prepare yourself after receiving the goods)

After the above materials are ready, please send the information to the salesman who docking with you. TONY will arrange technicians to guide the installation and debugging at the fastest speed.

More Projects

Leave Your Message

Email
WhatsApp